THE National Grid Corporation of the Philippines (NGCP) has energized the Toril-Bunawan 230 kilovolt (kV) transmission line, the final component of its Mindanao 230 kiloVolt (kV) backbone project.

Energization of the P7.09-billion backbone project components started with the power transformer in Villanueva Substation and Maramag-Villanueva 230kV Line 2 in September 2019, while the Balo-i-Villanueva Lines 1 and 2 were energized in September and October of the same year. Transformers in Bunawan Substation and the Maramag-Bunawan 230kV lines were energized also in October 2019. This was followed by the energization of another new transformer in Villanueva Substation and the Maramag-Villanueva Line 1 in November 2019, while a power transformer in Toril Substation was energized shortly after in the same month.

The Matanao-Toril 230kV Lines 1 and 2 were energized in December 2019 and January 2020, respectively, while the Matanao-Culaman 230kV Lines 1 and 2 were energized in the same period. The final component, the Toril-Bunawan 230kV Lines 1 and 2, were energized in November 2020, despite the difficulties posed by the varying lockdown protocols implemented across the country.

“With this completion, the line will supplement the existing Davao-Toril-Matanao 138kV transmission line in transmitting any and all available and incoming generation, ensuring transmission service reliability for the entire region,” said NGCP.

Among the generating facilities that will connect to the line are the GNPower Kauswagan Clean Coal-Fired Power Plant, Therma South Incorporated Power Plant, and San Miguel Consolidated Power Corp., with a total combined capacity of 1,440MW.

The grid operator said the Mindanao backbone project is seen to stabilize power transmission in the island. As one of NGCP’s critical projects, the Mindanao backbone will connect bulk generation from the northern and southern parts of Mindanao and ensure stable and continuous power from Lanao del Norte, passing through Agusan del Sur, all the way to Davao del Sur.

More importantly, the Mindanao 230kV backbone project is an integral part of NGCP’s Mindanao-Visayas Interconnection Project (MVIP), which will link the Visayas and Mindanao islands and realize sharing of power within the entire country.

“The Mindanao Backbone is critical to the MVIP because through this project, the new transmission line will accommodate the capacities needed to fully support and utilize the capabilities of the interconnection,” NGCP added.

NGCP is a Filipino-led, privately owned company in charge of operating, maintaining, and developing the country’s power grid, led by majority shareholders and Vice Chairman of the Board Henry Sy Jr. and Co-Vice Chairman Robert Coyiuto Jr.