David Celestra Tan

July 7, 2016

The debate on distributed generation versus centralized generation dates back to the time of Thomas Alba Edison, the inventor of electricity, when he built the Pearl Street Station in New York in 1882.

Napocor’s Philosophy of Centralized Generation

The policy of distributed generation got lost in the Philippines power development strategy when the government nationalized under Martial Law the power generation and transmission functions under the government owned monopoly, National Power Corp. One thing that Napocor’s and the old Ministry of Energy’s strategy got confused on was while it may be sensible for building bigger power plants in the large Luzon island, that centralized generation philosophy was adopted also in the Visayas and Mindanao. Consequently, under Napocor there were no major power plants built in Negros and Panay islands. Instead, they relied on the 700mw geothermal fields in Ormoc, Leyte and built overhead power lines to Cebu and connected Leyte, Cebu, Negros, and Panay with submarine power cable systems.

Meralco under its original American owners (from New York) and visionary Lopez patriarch Eugenio Lopez Sr. was building power generating plants close to the load center of Manila. Remember the Rockwell power plant in Makati, the Gardner Snyder station in Sucat, Tegen Power Station in Sta.Ana, and Malaya? These were feasible in their locations in Laguna Bay and Manila because they run on bunker c which can be barged.

Even the last big power project under Martial law, the 600mw nuclear plant in Morong, Bataan was not unreasonably far (120km) from the Metro-Manila load center. There was already a 230kv transmission line built from Morong to Hermosa Bataan. When this power project was aborted under the Anti-Marcos frenzy of 1986, there were no power projects undertaken to replace it despite having a supposed power guy appointed by President Cory Aquino to the presidency of the power monopoly Napocor.

Power Development in the Philippines was neglected during the political upheaval of 1980’s and caught up with the country just as it was starting to economically recover after the people power revolution. A five (5) year power crisis ensued with 12 hour rotating brownouts 1990 to 1995. The power projects undertaken under the Power Crisis Act giving new President Fidel V. Ramos the absolute power to negotiate urgent power projects, saw the building of power plants in places where coal unloading is feasible, where power barges can be moored, and where big power investments are politically convenient.

One of the emergency power projects in the 1990’s was the 700mw geothermal of Cal Energy in Ormoc, Leyte, built with a full off-take guarantee by the national government through PNOC. For many years it was being dispatched only 50% because its power cannot be delivered efficiently through the Visayan Grid which relies on submarine cables. During this period, Panay island and Negros had been suffering from power shortages including Boracay. In August of 1998, Leyte was connected to Luzon by a 440mw HVDC submarine cable system.

If we decide that the Bataan Peninsula is a good strategic generation area, it may be sensible to build a submarine cable system from Bataan to the Manila and Calabarzon load centers instead of going around Pampanga and Bulacan with overhead power lines that tend to run into right of way problems in building them.

An archipelagic and island-centric generation strategy is most critical for the Visayan islands because of the high cost of continually building submarine power cable systems. Its major islands of Panay, Negros, Cebu, and Leyte, are seeing booming economies. Of these islands the weak link in generation is the 250mw Negros where there has not been a major power plant built for 40 years other than the ill-fated 80mw Northern Negros Geothermal project of PNOC EDC in the Mt. Kanlaon area which PNOC, after investing billion pesos, turned out to be a 10mw area. Currently most of Negros power comes from a coal plant in Cebu and eventually a coal plant in Panay islands to the West which will both require the expensive expansion of the submarine cable systems from those islands to Negros, adding to the transmission charges to consumers. We heard this is budgeted at P5 billion to bring about 100mw of Panay generated power to Negros.

Negros island can eventually be self-sufficient in base-load power from Renewable Energy! But of the biomass kind not solar which if the DOE’s approval philosophy continues will reach an ill-advised 1,000 mw. Lets hope they require these FIT-spoiled solar projects to at least supply grid-compatible systems.

For power reliability in each island there has to be sufficient on-island generation. There is an esoteric term in the power sector called “N-1” which roughly means an island must be able to maintain normal power supply even if its largest power source like a generating unit or largest transmission system is down. This is embodied in the Philippine Grid Code as part of power reliability formula. The Code also encourages embedded generation.

NGCP as the system operator and planner of the power grid does not push for on-island generation. It is not their job they say. In fact their behavior suggests they are against it. They push for more revenue generating transmission line projects. And those will continually add to the transmission charges to the consumers.

At some point, the major islands of Mindoro and Palawan will need to be connected to the main grid. However, the scale and cost must be sensible. NGCP’s proposal to connect Mindoro island with a P11.9 billion 230kv submarine cable is an overkill and ignores the need to maintain on-island generation. Documents showed the 230kv sizing is for the purpose of accommodating a 300mw coal project where there is none on the island of Mindoro itself. And it was on its way to approval by the old ERC! Had they proposed a more sensible 69kv connection line to provide supplementary power it would have been more viable. Of course, they have to address how to protect Mindorenos from the loss of the missionary subsidies.

The same with the 250 kilometer long Palawan island, cited for being one of the most beautiful islands in the world. It may eventually be connected to the Luzon or Mindoro grid but for peaking and reserve power. For now the major task for at least the next 5 years is building as much on-island generating capacity as possible to meet its 40mw demand. Palawan is a wonderful place for the government to aggressively push for Renewable Energy. It has hydro, biomass, and wind potential. Also grid-compatible solar. Why are they insisting on building a coal plant that the Palawenos are against? It can sabotage the clean and pristine image that the island needs for its tourism, the most logical driver of economic development of the island.

A lot of big generating projects and submarine cable projects are already in place. But it is not too late to establish a better rhyme and reason for their locations and the purpose and sizing in the transmission development plan. It takes time to create sensible power projects and it will also take time to undo the cost to consumers of ill-advised projects. But it will have to start with a spark of reason triggered by a visionary. Let us hope Secretary Al Cusi can provide a new direction in the nick of time and we can change course towards what is sensible and seemed obvious – archipelagic generation for an archipelagic nation.

It will help assure consumers are charged transmission wheeling rates that are reasonable and based on a carefully planned transmission development strategy.

Matuwid na Singil sa Kuryente Consumer Alliance Inc.

Matuwid.org

Leave a Reply

Your email address will not be published. Required fields are marked *