May 14, 2019

ERC: Implications of high court’s PSA ruling ‘massive’

By Jordeene B. Lagare – May 11, 2019 from The Manila Times THE Supreme Court’s (SC) recent decision to subject power supply agreements (PSAs) made on or after June 2015 to public bidding presents “massive” implications, the Energy Regulatory Commission […]
April 29, 2019

Subic power plant faces further delay

By Alena Mae S. Flores – April 28, 2019 at 07:10 pm from manilastandard.net Redondo Peninsula Energy Inc. may put on hold the development of a 660-megawatt coal-fired power until 2020 due to construction issues, an official said over the […]
January 14, 2019

RP Energy cancels contract for coal-fired plant in Subic

By Lenie Lectura – January 14, 2019 from Business Mirror REDONDO Peninsula (RP) Energy Inc., a partnership among the Manila Electric Co. (Meralco), Aboitiz Power Corp. and Taiwan Cogeneration Corp. through their respective subsidiaries, has canceled the limited notice to proceed issued […]
June 13, 2018

Devanadera inhibits on PSA decision for Atimonan plant

By Myrna M. Velasco – June 12, 2018, 10:00 PM from Manila Bulletin Having been a legal consultant at the pre-development phase of the project, Energy Regulatory Commission (ERC) Chairperson Agnes T. Devanadera forthrightly told media that she will inhibit […]