By Alena Mae S. Flores – September 4, 2023, 8:15 pm
from manilastandard.net

Power retailer Manila Electric Co. said Monday it energized a new smart substation in Taguig City to ensure the provision of stable and reliable power for Ayala Land Inc.’s Arca South development and the adjacent communities in the area.

The P597-million 115 kV-34.5 kV gas-insulated switchgear substation was commissioned with an initial capacity of 83 megavolt amperes but will ultimately house three transformer banks with a combined capacity of 249 MVA to support the existing and future energy requirements of the Arca South development—a new business and lifestyle district in Taguig City.

The Arca South substation will also improve voltage regulation in parts of Taguig City, provide operational switching flexibility during contingencies, and contribute to system loss reduction in the area.

Meralco executive vice president and chief operating officer Ronnie Aperocho said the development of the Arca South substation forms part of Meralco’s support to commercial customers like Ayala Land which play a vital role in the country’s economic growth and development.

“The opportunity to participate in the master planning of Ayala Estates has allowed Meralco to serve more customers and further cement our commitment to keep the lights on. As a testament to that, this newly energized smart substation in Arca South Taguig will provide safe, adequate, and reliable capacity to serve the existing and future power requirements of this particular Ayala Land development, and the adjacent communities in the area,” Aperocho said.

The Arca South project is the latest development in Meralco’s longstanding partnership with the Ayala Land.

Meralco energized nearly a hundred projects of Ayala Land and subsidiary Makati Development Corp., including One Ayala and Seda Manila Bay. Ayala Land consistently provides a substation lot provision for its estate developments.

“We share a common goal which is to uplift the lives of our people and we encourage the active participation and engagement of the private sector in the present economic programs,” Meralco chairman and chief executive Manuel Pangilinan said.

Meralco has been investing heavily in projects that will not just improve its electricity distribution system but also contribute to ensuring the infrastructure support to the government’s nation-building efforts.

Communities and establishments that will benefit from the new substation include AC Health’s Healthway Cancer Care Hospital, Ayala Malls Arca South, Alveo Veranda, Avida Towers Vireo, Landers Superstore Arca South, Maharlika Village, Puregold FTI Taguig, Sunshine Mall Plaza, Taguig Pateros Hospital and Technological University of the Philippines-Taguig.

“As we continue to build upon the foundations of Arca South, we are ensuring that the energy needs of this community are met with efficiency and resilience. This substation represents more than just a physical structure; it represents our dedication to sustainable urban development. It is a cornerstone of progress, enabling us to power homes, businesses, and innovations that will drive Arca South’s growth and development,” Ayala Land senior vice president and group head for Ayala Land Estates Robert Lao said.